Draft ordinance would require 50 percent construction before hydropower IPOs
A draft ordinance would write into law a rule that hydropower projects must reach 50 percent physical progress before an IPO, a threshold the Electricity Regulatory Commission already applies. Investors and developers are split, The Kathmandu Post reported.
The government is preparing legal changes that would require hydropower companies with projects under construction to complete at least 50 percent of their physical work before they can launch initial public offerings (IPOs), The Kathmandu Post reported.
The rule is in a draft of the Ordinance to Amend Some Nepal Acts Related to Investment and Infrastructure, 2026, which proposes amending several laws, including the Securities Act. Under the draft, a company developing a hydropower project could apply for a public share offering once the project reaches at least 50 percent certified physical progress and meets the other requirements for a public issue. An application could not be rejected solely because the project has yet to begin commercial production, the Post reported.
A 50 percent physical progress threshold already applies under Section 4, Sub-section (5) of the Electricity Regulatory Commission's Directive on Prior Approval and Regulation for Public Share Issuance of Electricity Companies, but it is not in the Securities Act or its regulations. The Post reported that writing it into the Act would make it harder to change, because an amendment would need parliamentary approval, while the regulator can revise a directive on its own.
Investors and developers split over the threshold
Share investor Keshav Koirala said allowing IPOs after only 50 percent of construction would hurt the stock market, and that hydropower companies should be allowed to issue shares only after they begin generating electricity. A high-level commission chaired by former finance minister Rameshore Khanal had earlier recommended the same, the Post reported. Investors' concerns also stem from a separate draft directive from the Securities Board of Nepal on general eligibility for public offerings, which would require companies to show a record of continuous business operation before issuing shares, though it allows different standards across sectors.
A study committee coordinated by Phanindra Gautam, a former Securities Board director, also recommended letting hydropower companies issue shares only after at least 50 percent of physical construction is complete. Its report found that converting most promoter shares into ordinary shares right after the lock-in period ended had created operational difficulties for listed companies outside the banking, financial services and insurance sectors. It also cited years without dividends, financial performance that fell short of projections made at the time of IPOs, and rising project costs at hydropower companies, the Post reported.
Developers oppose the proposal, arguing it would cut off funding at the stage when they depend on it most. Ganesh Karki, former president of the Independent Power Producers' Association, Nepal (IPPAN), said hydropower companies need substantial funding in the early stages of project development, and that blocking them from raising capital through IPOs at that point would be misplaced. He said the government should instead strengthen oversight of construction and make sure investors' money stays protected after a company is approved to issue shares.
Subas Chandra Dhungana, a share investor and analyst, said one standard for every hydropower project would be inappropriate, since some large projects take years to build and finishing the remaining half after approval could take several more years and raise costs. He said eligibility should take account of factors such as a project's generation capacity and the deadline for starting production, and that companies should not be barred from IPOs merely because they have not begun generating electricity.
Other requirements in the draft
The draft amendment would also require hydropower companies to have their construction progress verified by an independent, qualified technical evaluator, and to disclose total project costs, outstanding construction work, additional funding needs and confirmed sources of finance. In the prospectus they would have to set out construction progress, possible delays, cost overruns and other major risks, along with the status of power purchase agreements, generation licences and other regulatory approvals, and the estimated completion date and the expected start of commercial generation. They would also have to give a clear plan for using the proceeds, ensure the money is spent on the project's approved purposes, and meet other requirements set by the Securities Board of Nepal.
The measure is still a draft. The government has yet to decide whether to bring the changes through an ordinance or as a bill in Parliament, the Post reported.