Key facts

  • The 456-megawatt plant has had no Indian export approval since the Nepal Electricity Authority first applied in April 2021.
  • Nepali officials believe a Chinese contractor's role is the reason; India has not said so formally.
  • India's 2021 rules let it bar imports from projects financed, owned or controlled from bordering countries without a power-sector agreement.
  • On November 17 Nepal received approval to sell 56 megawatts on India's energy exchange until July 31, 2027, and to import up to 350 megawatts this winter.