Upper Tamakoshi still has no India export approval despite fully domestic funding
Nepal's 456-megawatt Upper Tamakoshi plant, financed entirely at home, has had no Indian approval to export power for over five years; Nepali officials link the delay to a Chinese contractor, Setopati reports.
Nepal's 456-megawatt Upper Tamakoshi Hydropower Project has still not received Indian approval to export electricity, more than five years after Nepal first asked, Setopati reported on November 17. Domestic institutions financed the whole project, including its loans. Nepali energy officials understand India to be withholding approval because a Chinese company was one of the project's contractors, though India has not said so formally.
The Nepal Electricity Authority, Nepal Telecom, the Citizen Investment Trust and Rastriya Jeevan Beema Company together hold 51 percent of the shares. The rest is held by the public, Dolakha residents, contributors to the Employees Provident Fund and the project's staff. The Chinese firm Sinohydro won the contract for the dam and tunnel through international competitive bidding, while two Indian firms and an Austrian company worked on other parts of the construction.
India's rules on projects linked to Chinese firms
India's 2021 procedure for cross-border electricity trade requires each hydropower project to get its own approval. It also says imports may be barred from projects that are financed, owned or controlled by companies from a country that borders India and has no power-sector cooperation agreement with it. According to Setopati, the rule is aimed mainly at projects with Chinese investment. Upper Tamakoshi was not built with Chinese investment and no Chinese company owns it; the Chinese firm only held a construction contract. Nepali officials read India's reluctance as a response to that contractor's role.
The Nepal Electricity Authority first wrote to India in April 2021 seeking permission to export power from Upper Tamakoshi and other projects. The plant began generating that July. In June 2023, during a visit to India, then Prime Minister Pushpa Kamal Dahal asked Prime Minister Narendra Modi to approve a further 1,200 megawatts of exports, including from Upper Tamakoshi. Setopati notes that India has approved exports from many other Nepali hydropower projects, large and small, but not from the largest plant built with Nepal's own money.
Prime Minister Balen Shah is due to visit India soon. Ratopati reported that Nepal's energy priorities for the trip include ending the annual renewal of export permits and pressing for effective implementation of the 25-year agreement to trade 10,000 megawatts over ten years.
Annual renewals add uncertainty
India decides which plant may sell how much electricity in which market, Setopati reported, and a plant's export approval is normally given for one year; some have received shorter ones. On November 17 the Nepal Electricity Authority received approval to sell 56 megawatts from three hydropower projects on the Indian Energy Exchange (IEX), valid until July 31, 2027. The Kathmandu Post reported that India's Central Electricity Authority separately allowed the Nepal Electricity Authority to import up to 350 megawatts through the exchange for the same period, as the authority expects domestic generation to fall short of demand for four winter months.
A senior authority official told Setopati that a medium-term contract to supply 609 megawatts to Haryana, Uttar Pradesh and Bihar expired at the end of October. The authority planned to sell that power on the exchange instead, but had not received approval for a proposal it sent in August. The official added that the export permits for four projects, about 98 megawatts in all (Upper Chameliya, Seti River, Upper Tadi Khola and Upper Dordi A), were renewed only in early October, not on time.
Nepal also runs a large goods trade deficit with India. In fiscal year 2025/26 (2082/83 BS) it imported goods worth about Rs 1.21 trillion from India and exported about Rs 259 billion, a deficit of about Rs 952 billion, Setopati reported.